Southern Province Cement Company announces the delay of operating the third mill in Jazan plant

Referring to the company’s announcement on 20/6/2011 regarding the operation of the third mill in Jazan Cement Plant within (10) months from the date the contract was signed on 19/6/2011, the company announces that the said project shall be delayed for (5) months for reasons beyond the company’s control, as the manufacturing company (Christian Pfeiffer) was late in submitting the civil works drawings.

It is expected that the operation of the third mill shall be on 20/9/2012, God willing.