Southern Province Cement Company announces the delay of the operation of the third mill in Jazan Plant

Further to the company’s announcement on 29/4/2012 regarding the delay of the operation of the third mill in Jazan plant, the company announces the delay of the project for further (4) months for reasons beyond its control, as the manufacturing company (Christian Pfeiffer) has delayed the approval of the civil drawings and the shipment of […]

Southern Province Cement Company announces the delay of the operation of the third mill in Jazan Plant قراءة المزيد »

شعار spcc logo

Southern Province Cement Company signs a contract for expanding the power station in Jazan plant

HH prince Abdullah bin Mosa’ad bin Abdulrahman Al- Saud, the chairman of Southern Province Cement Company, in the presence of the directors, has signed a contract with the deputed director of Wartsilla Power Contracting Company of Finland for the execution of the expansion of the power station in Jazan plant by adding four diesel units,

Southern Province Cement Company signs a contract for expanding the power station in Jazan plant قراءة المزيد »

شعار spcc logo

Southern Province Cement Company announces signing a contract for the execution of a third production line in Tahama Plant

HH Prince Abdullah bin Mosa’ad bin Abdulrahman Al- Saud, Chairman, in witness of the Directors, has signed a contract with Mr. Wu Shoufu, President of Sinoma International Engineering Company Ltd., for the execution of the third production line in Tahama Plant. The event took place on the afternoon of this Wednesday 9/7/1433h corresponding to 30/5/2012.

Southern Province Cement Company announces signing a contract for the execution of a third production line in Tahama Plant قراءة المزيد »

شعار spcc logo

Southern Province Cement Company announces the delay of operating the third mill in Jazan plant

Referring to the company’s announcement on 20/6/2011 regarding the operation of the third mill in Jazan Cement Plant within (10) months from the date the contract was signed on 19/6/2011, the company announces that the said project shall be delayed for (5) months for reasons beyond the company’s control, as the manufacturing company (Christian Pfeiffer)

Southern Province Cement Company announces the delay of operating the third mill in Jazan plant قراءة المزيد »

شعار spcc logo

Southern Province Cement Company announces starting the commercial production of the second line in Tahama plant

Further to its announcement dated 11/2/2012, Southern Province Cement Company announces starting the commercial production of the second line in Tahama plant on 1/3/2012. The production has reached 5,000 tons/day by now, which matches the nominal capacity as per the contract. With this, the production of Tahama plant has increased to reach 10,000 tons/ day.

Southern Province Cement Company announces starting the commercial production of the second line in Tahama plant قراءة المزيد »

شعار spcc logo

Southern Province Cement Company announces Signing a contract for the delivery of a third mill in Jazan plant

His Highness Prince Abdullah bin Musa’ad bin Abdurrahman Al- Saud, the chairman has signed a contract with Mr. Erich Pichlmaier, the MD of the German company, Christian Pfeiffer, for the delivery of a third cement mill for Jazan plant. The contract consist of delivering the full mechanical and electrical equipment, the design, the supervision of